Widening of Unser Blvd from a 2-lane road to a 4-lane road from Cherry Road to Paseo del Volcan. The Project will include a pedestrian path, sidewalks, and bike lanes.
A virtual public meeting was held on July 24, 2024 at 6 pm.
To view the presentation given at the virtual public meeting, click here.
A second virtual public meeting was held on October 2, 2024, at 6 pm.
February 2026: All NMDOT project certifications received and Final Plan Review conducted with NMDOT
December 2025: Coordination with NMDOT for project certification on-going -- Utility certification requested
November 2025: Coordination with NMDOT for project certification on-going -- Environmental Finding of No Significant Impact (FONSI) Re-evaluation approved and Right of Way certification requested
October 2025: Coordination with NMDOT for project certification on-going -- Railroad certification received
September 2025: Continuing Utility Coordination and Preparation of Environmental Certification
August 2025: Continuing Utility Coordination and Preparation of Environmental Certification
June 2025: Continuing to prepare NMDOT Certifications
April 2025: Submit draft right of way certification to NMDOT and continue utility coordination
January 2025: Preparing NMDOT Certifications
December 2024: Progressing to 100% design
November 2024: Design Amendment for additional ADA upgrades
October 2024: Conduct public meeting, complete Pre-Final design, and conduct Pre-Final review
September 2024: Progressing design to Pre-Final and drafting NMDOT certifications
August 2024: Progressing design to Pre-Final
July 2024: 90% Review Meeting with NMDOT and Public Meeting
June 2024: Updating 90% Design and Schedule Public Meeting
May 2024: Updating 90% Design
April 2024: Corridor Walk and Field Review Meeting