Contracted Neighborhood Streets Improvement Project

Project Manager: Timothy Archuleta
Office Phone: (505) 896-8775
E-Mail: tarchuleta@rrnm.gov
Contract Company: G.M. Emulsion
Cost: $1,500,000
Stage: Construction
Schedule: March 2023 - June 2023
NeighborhoodStreetsThumbnail

Crack patch & seal of residential roads throughout the City of Rio Rancho. Hours of operation will be Monday-Friday, 7am-5pm. Construction will begin on 3/13/2023 through 6/30/2023.

Traffic control will be limited to 1 lane closure at a time. Residents will have access to their properties at all times during construction.