A.D.A. Ramp Remediation Projects within Enchanted Hills and Northern Meadows

Project Manager: Timothy Archuleta
Office Phone: (505) 896-8775
E-Mail: tarchuleta@rrnm.gov
Contract Company: Altor Construction
Cost: $450,808.78
Stage: Construction
Schedule: February 2023 - May 2023
SG 16

Removal of non ADA compliant ramps and installation of ADA compliant ramps within areas of the Enchanted Hills and Northern Meadows Subdivisions. Work will be completed Monday-Friday during the hours of 7am-5pm. Construction is began on 2/13/2023 and is anticipated to be completed by 05/26/2023.

No lane closures during the life of the project. Sidewalk and bike lane closures only within the project limits.

Funding for this project is from Community Development Block Grant, Housing and Urban Development Block Grant Funds.

FS2187 Project Area