District 1

Project Manager: Bill Ladd
Office Phone: 505-891-5032
E-Mail: bladd@rrnm.gov
Contract Company: Albuquerque Asphalt, Inc.
Cost: $2,095,774.43
Stage: Construction
Schedule: June 2023 - September 2023
Hybrid Mill

This is a Hybrid Mill & Inlay paving project that will replace the existing asphalt with new pavement and create an improved road base.  In addition, a new water line with service lines will be installed as part of this project. This is phase 1 of a project that is intended to address residential roadways throughout the community in need of maintenance beyond crack patch and sealing work.

Project Status
  • Phase I - Water lines complete. Roadway paving begins July 5, 2023 and will be ongoing through July 21, 2023.
  • Phase II - Begins July 5, 2023. Tarpon Ave. detour from 9:00a.m. to 3:00p.m. on July 13, 2023.
DistrictOneCombinedPhasing
DistrictOnePhase1
057886 - Albuquerque Asphalt - Hydra Rdand Tarpon Ave - 4-Way Stop and Flagman
DistrictOnePhase2
058110 - Albuquerque Asphalt - Tarpon Ave BT Hydra Rd and Bravo Ct - SB OWRC and Flagman_Page_1
058110 - Albuquerque Asphalt - Tarpon Ave BT Hydra Rd and Bravo Ct - SB OWRC and Flagman_Page_2
Albuquerque Asphalt - Tarpon Ave BT Hydra Rd and Bravo Ct - SB OWRC and Flagman Pg2