King Boulevard Expansion Project

Project Manager: Bill Ladd
Office Phone: (505) 891-5032
E-Mail: bladd@rrnm.gov
Contract Company: Albuquerque Asphalt Inc.
Cost: $  8,055,618.24
Stage: Construction
Schedule: January 2023 - November 2023
IMG_0759

The King Boulevard Expansion project from Wilpett Drive to Unser Boulevard includes reconstructing and expanding King Boulevard from two lanes to four lanes, installing raised medians, curb and gutter, concrete sidewalk, concrete curb ramps which comply with the Americans with Disabilities Act (ADA), asphalt multi-use path, sanitary sewer main line and services, water line services, storm drain/detention pond modifications, intersection lighting, pavement markings, landscape gravel, and constructing a roundabout at the Wilpett Drive intersection.

Status Log:

  • October 2023: Substantially completed.  Awaiting electrical work.
  • January 2023: Notice to Proceed

The following restriction/detour route will go into effect on March 6, 2023 and last through mid-April 2023.

Adobe Disclaimer: Reading the PDF documents provided on this site requires the Adobe Acrobat Reader, available for free from Adobe. Adobe, the Adobe logo, Acrobat, and the Acrobat logo are trademarks of Adobe Systems Incorporated.